Project Details
Mactan Rock Pipe Laying Lapu-Lapu City
- 75 ln.m. Pavement Cutting
- 18 cu.m Pavement Breaking
- 12.42sq.m. Subgrade Preparation
- 115 cu.m Excavation
- Hauling of Excavation Materials
- 124 cu.m. Sand Bedding
- 18 ln.m. Pipe Jointing 400 mm PE100-SDR13.6
- 18 ln.m. Pipe Laying
- 9.45 cu.m. Backfilling with Compaction
- Warning Tape Laying